Mekeran Energy & Infra is delivering a complete solar plant with N-Type TOPCon panels. The 110 kV infrastructure and project substation are already complete.
Project Highlights
A turnkey plant, from development and EPC execution to grid connection.
- Project capacity
- 9 MW
- Location
- Poomalaikundu, Theni, Tamil Nadu
- Technology
- N-Type TOPCon solar panels
- Project scope
- Turnkey solar project
- 110 kV transmission line
- Completed
- Project substation (PSS)
- Commissioned 31 March 2026
- Project status
- Under execution
- Scheduled commissioning
- December 2026
Where The Project Stands
The grid-side work is finished. Plant execution is now underway ahead of the December 2026 commissioning.
110 kV transmission line
Completed
Project substation
Commissioned 31 March 2026
Plant execution
In progress
Commissioning
December 2026
Operational Excellence On Site
Progress photos from the Theni project site at Poomalaikundu.




One Partner For Solar And Power Solutions
We develop and build solar projects for captive, Open Access and ISTS use, including wind-solar and battery hybrids.
Solar EPC
Turnkey EPC up to 100 MW, from concept to commissioning.
Project development
Intra-state captive, Open Access and interstate ISTS solar projects.
Solar parks
Land, infrastructure and evacuation facility for 50 MW across 4 locations.
Wind–solar hybrid
Hybrid models with wind and battery storage for steadier supply.
Operation & maintenance
Central monitoring and field service for plants, 365 days a year.
Power trading
Customised energy solutions, including Open Access arrangements.
What You Can Count on
Let's Build Your Next Solar Project
We would be glad to explore opportunities with your organisation and build a long-term association. The project profile is available on request.
- Solar EPC
- Renewable energy projects
- Open Access
- Customised energy solutions